On August 16th of this year City Council read aloud all sealed bids received for the resurfacing of several sections of City Streets. Two bids were received from
the companies of: “Shelly Company, Inc.” and “Shelly & Sands Inc.”
Shelly & Sands Inc. submitted the lowest bid at 44 dollars per ton of ODOT item 404 asphalt concrete. At the regular meeting of City Council on September 6th, City Council approved a contract with Shelly
& Sands Inc. to perform the resurfacing job. The City issued a notice to proceed to the Contractor requesting that the work begin on September 26th. The Contract time for completion is 19 consecutive
calendar days beginning on the 26th. The Contract deadline to complete the work is therefore October 14th. The funds used to pay for the project will be provided by the City Street Resurfacing
Line and the General Fund Permissive Line.
These lines are funded through the City income tax and the State Gasoline Tax respectively. For more details concerning the areas to be resurfaced please contact the City Street Superintendent between the hours of 7 A.M. and 3 P.M. Monday through Friday.
|